Hillside Road Bridge
over the DuPage River
Client: City of Naperville
Location: Naperville, Illinois
Construction Completed: 2001
Construction Cost: $850,000
Challenge
The historic Naperville Riverwalk is a significant piece of history
of the area. The Hillside Road Bridge spans the West Branch of
the DuPage River near downtown Naperville. The City of Naperville
contracted Bowman, Barrett & Associates Inc. (BB&A) to
provide complete preliminary engineering services for the rehabilitation
of the existing three-span, precast, prestressed concrete deck
beam structure. Final design approval was given to use a special
cast-in-place, post-tensioned, continuous concrete slab for the
superstructure replacement and widening.
The goal was to design an architecturally pleasing structure that
fits into the surrounding residential and riverwalk environment.
Details
BB&A provided the following services on this project:
- Field survey
- Bridge inspection
- Hydraulic/drainage studies
BB&A prepared the following for the client:
- Hydraulic report
- Bridge condition report (BCR)
- Project development report (PDR)
- Type, size and location (TS&L)
plans
Final Design approval was granted in June 2000. BB&A prepared
final construction documents to include plans, special provisions,
cost and time estimates. Final design was completed by the end
of 2000 in preparation for a March 2001 letting. BB&A also
provided Construction Engineering Services to the City on this
project.
|